The Laboratory prepares its ES&H
Management Plan (the Plan) annually in accordance with the guidance
provided by DOE-HQ, DOE-CH, and the Fermi Group. The process
used to develop the Plan combines top-down guidance from the Department
with bottom-up analysis and decision-making by Fermilab line managers
and ES&H professionals. The risk-based resource constrained
process is used by Fermilab to optimize available resources to
manage ES&H. Utilizing this approach, Fermilab management
has been able to consistently ensure that ES&H risks are being
adequately addressed within the Lab's budget.
The initial Plan developed for FY96 activities
was prepared in April of 1994, and then updated in April of 1995.
In April of 1996, while preparing the FY98 Plan, Fermilab evaluated
its progress to date with respect to accomplishing ES&H activities
planned for FY96 and updated the FY97 portion of the FY98 Plan
accordingly. This report evaluates Fermilab's FY96 ES&H posture
by evaluating the Lab's ES&H risks, compliance status, and
Tiger Team Corrective Action Plan progress. This report also
compares and analyzes planned versus actual ES&H activities
and expenditures.
A. ES&H Risks
Since the closeout of the Category 2
Tiger Team findings (Lockout Tagout, Confined Space Entry, and
Electrical Safety), no significant risks have existed at Fermilab.
The risks associated with operating systems and equipment to
conduct HEP research (radiation, electricity, hazardous chemicals
and gases, etc.) are all being managed through the training of
appropriate personnel, drafting and using adequate procedures,
and operating and maintaining equipment and systems within accepted
safety limits.
B. Compliance Status
For the most part, Fermilab is in compliance
with all applicable safety and health regulations and Illinois
Environmental Protection Agency (IEPA) statutes. Most compliance
and improvement efforts underway are concerned with upgrading
already existing programs and achieving full compliance with 29CFR1910
(OSHA) standards. These efforts include asbestos abatement and
personal protective equipment (PPE) upgrades. Efforts are also
underway to achieve full compliance with the applicable portion
of the National Fire Protection Association (NEPA) code. In FY1996,
Fermilab achieved compliance with the Radiation Protection Standard
(10CFR835) and the Department of Transportation (DOT) regulations
concerning site access and public roadways. Efforts underway
throughout FY96 and continuing in FY97 involve the installation
and operation of automatic gates to control site access.
C. Major ES&H Initiatives
Over the past year and a half, Fermilab
has undertaken a significant ES&H effort aimed at determining
and implementing the set of Work Smart (formerly known as Necessary
and Sufficient) standards by which safe operations of the Lab
will be assured. Determination of the applicable set of Work
Smart standards was completed in July of 1995, at which time this
set of standards was adopted into the Fermilab contract. This
initiative streamlined many of the Lab's ES&H administrative
functions and resulted in some reductions in planned ES&H
compliance activities that remained "on the books" from
the 1992 Tiger Team Assessment.
D. Funding Reduction
In FY94, the Lab's HEP operating budget
was $171M. As such, when the FY96 Plan was first being prepared
in FY94, the Lab assumed, for planning purposes, that its FY96
budget would be the same as FY94 (i.e., $171M). In actuality,
the Fermilab HEP operating budget for FY96 (after subtracting
out funding specified for the Compact Muon Solenoid and Large
Hadron Collider projects, the Positron Emission Topography project,
and the monies transferred from plant to operating) was $168M.
Utilizing a 3% inflation factor for 1994 and 1995, the Lab's
actual operating budget of $168M in FY96 represents a $13M decrease
in available funding from FY94 to FY96.
E. Reduction of ES&H Personnel
Since preparation of the first draft
of the FY96 Plan in April of 1994, Fermilab has reduced its staffing
by approximately 100 persons. Of these 100 persons, approximately
14% were ES&H professionals. Total ES&H staffing at Fermilab
has gone from an estimated 163 FTEs in FY94 to 148 FTEs in FY95
to 136 FTEs in FY96. Some of these reductions were due to the
reassignment of personnel to other programmatic activities at
the Lab; others were reductions in force. Through this transition
period, Fermilab has managed it personnel reduction effectively
so that these ES&H reductions have not caused any unsafe or
noncompliant working conditions. Additionally, this reduction
in staffing has not resulted in any significant shortages in ES&H
personnel skill mix nor has the lack of ES&H support delayed
any planned programmatic operations.
F. Compliance and Improvement Activity
Backlog
Throughout late FY95 and FY96, Fermilab
determined and began to implement its set of Work Smart standards.
Implementation of these Work Smart standards reduced the backlog
of some 47 Tiger Team tasks which in previous years of the ES&H
Management Planning Process had been ìbundledî into
a number of low priority Compliance and Improvement Activity Data
Sheets (ADSs). This reduction of 47 Tiger Team tasks translated
into an elimination of 22 ES&H ADSs saving approximately $11M.
G. ES&H Accomplishments
In FY96, Fermilab completed work on and
closed out some 18 compliance and or improvement ADSs in accordance
with funding and risk reduction profile established by its ES&H
Management Plan. The remaining compliance and improvement ADS
backlog is minimal and will be updated again in the Spring of
1997 during the development of the FY99 ES&H Management Plan.
A specific breakout of activities, including General Plant Projects,
completed can be found in Attachment A.
H. Planned versus Actual ES&H Expenditures
A comparison of planned versus actual
expenditures for FY96 shows that Fermilabís actual ES&H
expenditures differ from those planned by less than 3%. (Note:
Fermilabís actual ES&H expenditures are greater than
97% of the planned ES&H resources.) The comparison of planned
versus actual ES&H expenditures ($ Thousands), for the various
Fermilab divisions and sections, is shown by the table below:
|
| |
| Direct | ||
| Accelerator | $1575.5 | $1579.0 |
| Research | 1265.9 | 1250.6 |
| Computing | 78.6 | 72.8 |
| Tech Support | 488.9 | 377.2 |
| Physics | 117.0 | 108.4 |
| Indirect | ||
| FESS | 1088.0 | 759.5 |
| Business Services | 207.9 | 170.3 |
| Lab Services | 399.6 | 423.3 |
| Directorate | 154.7 | 140.9 |
| ES&H | 3985.0 | 4331.7 |
| TOTAL | $9361.1 | $9213.7 |
I. FY1996 ES&H Conclusions
A year end review of the Fermilab ES&H
Management Plan for FY96 shows that actual ES&H activities,
expenditures and accomplishments track very closely with those
that were planned. Over the past year, Fermilab has made significant
progress in ìworking offî its Tiger Team legacy and
implementing a set of Work Smart standards while managing the
Labís downsizing and subsequent reduction of ES&H personnel.
Throughout FY96, Fermilab conducted its operations in a safe,
compliant , and cost-effective manner.
Perhaps more than any other Energy Department
site or facility, Fermilab has made significant progress in closing
out its Tiger Team findings and upgrading its compliance posture.
During FY 1996, an additional 40% of the Tiger Team tasks were
closed out, leaving less than 7% remaining open at the end of
FY 1996. The progress to date is shown by the graph below:
Nearly as remarkable has been Fermilabís ability to consistently manage its operations in a way that both improves the Labís compliance posture but more importantly reduces the Labís worker injury cost index. In the future, a goal will be to also reduce worker injury rates. The results of Labís the ten-year injury cost index are shown by the graph below:
While Fermilab has successfully improved
the safety controls of many Lab operations, upgraded its compliance
status, and managed its reduction in ES&H personnel, many
challenges still remain concerning the management of ES&H
activities including realignment of the various ES&H functions
to support the new Lab organization: Beams Division, Computing
Division, Particle Physics Division, and Technical Division.
Additionally, Fermilab line and ES&H managers will continue
to focus on the challenges associated with lowering occupational
injuries and illnesses, minimizing ergonomic effects, achieving
full compliance with the approved set of Work Smart standards,
and implementing an effective ES&H assessment program.
As the DOE sites and facilities move to develop and implement Integrated Safety Management Systems (ISMS) in response to Defense Nuclear Facilities Safety Board Recommendation 95-2, Fermilab finds that it has met most, if not all, of the objectives of the ISMS through its 1) determination and implementation of Work Smart standards, 2) development and implementation of aggressive employee (ES&H) training programs, 3) implementation of procedures and rigorous work center standards (conduct of operations, maintenance management, accelerator safety, lockout tagout, etc.), 4) utilization of the ES&H Management Planning process to integrate ES&H into the Labís systems to plan, budget, execute and monitor work, and 5) pursuit of a tri-partite assessment program to ensure superior ES&H performance and continued line management ownership and accountability for ES&H. At Fermilab, Integrated Safety Management has been a way of conducting HEP research throughout the 1990's.