Training Risk Summary

Likelihood\Consequence Insignificant Minor Moderate Major Extreme
Rare 1 2 3 4 5
Unlikely 2 4 6 8 10
Possible 3 6 9 12 15
Likely 4 8 12 16 20
Almost Certain 5 10 15 20 25

Key
Consequence safety and health / equipment and components / Fermilab brand / project or experiment / environmental
Insignificant first aid only, no lost time / negligible damage to equipment / no significant risk to brand reputation / negligible impact to project / no measureable impact to environment
Minor medical attention required, no lost time / minimal damage to equipment / minimal risk to brand reputation / minor impact to project / minor impact to environment
Moderate additional medical attention required with lost time / major damage to equipment / likely risk to brand reputation / significant impact to project / serious impact to environment
Major severe health impact with lost time / loss of equipment and components / significant risk to brand reputation / risk of project failure / long-term impact to environment
Extreme severe, irreversible injuries or death / loss of multiple pieces of equipment and components / damage to brand / project failure / permanent impact to environment

Key
Risk Requirement
≤6 Training must be completed within 60 days of ITNA or last completion date.
>6&≤12 Training must be completed within 30 days of ITNA or last completion date.
>12 Training must be completed within 10 days of ITNA or last completion date.